| Reference | 75317/APP/2022/3468 |
| Status | Approval |
| Proposal | HS2 request for approval of Bringing Into Use, under condition imposed by Schedule 17 of the High Speed Rail (London - West Midlands) Act 2017, relating to a temporary railway siding (1.057 kilometres in length) covering an area of 0.75 hectares, commencing approximately 70m west of the bridge carrying B466 High Road over the Chiltern main line, terminating on the bridge carrying Breakspear Road over the Chiltern main line including, a bridge over the River Pinn. |
| Location | RAILWAY SIDINGS W/O HIGH ROAD OVER CHILTERN MAIN LINE BREAKSPEAR ROAD RUISLIP |
| Ward | ICK/HAM & S HF/D 22 |
| Case Officer | Karl Dafe |
| Received | 09-11-22 |
| Validated | 15-11-22 |
| Decision By | 10-01-23 |
| Neighbours | Consultation Started : 28-12-22, Comments Due : |
| Decided | 20-12-22 |
| Agent | Mrs Lucy Neal Skanska Costain Strabag Joint Venture (Area WestCore Office) 3 Ickenham Road Ruislip HA4 7DQ |