PLANNING APPLICATION DETAILS
Reference75111/APP/2025/2525
StatusUndecided     
ProposalDetails pursuant to the partial discharge of Condition 17 (Drainage Verification) in relation to Union Park 2 (UP2) and UP3 only as attached to planning permission ref. 75111/APP/2020/1955 dated 15-04-2021 (Site clearance and preparation, including the demolition of remaining buildings, and the redevelopment of the site to provide: a new data centre (Use Class B8), a HV Sub-Station, works to the highway, car parking, cycle parking, associated infrastructure, enclosures and necessary physical security systems, hard and soft landscaping (including works to the River Crane) and ancillary uses, as well as associated external works.)
LocationLand at Bulls Bridge Industrial Estate NORTH HYDE GARDENS HAYES UB3 4QQ
WardPINKWELL 2022
Case OfficerMichael Briginshaw
Received30-09-25
Validated13-10-25
Decision By27-02-26
NeighboursConsultation Started : ,     Comments Due :
AgentNick Heard 5th Floor 2 Kingsway Cardiff CF10 3FD